A business that runs SAP's older ERP has a date in front of it. SAP's own maintenance strategy says mainstream maintenance for the core applications of Business Suite 7, the family that includes ECC, runs to the end of 2027, with optional extended maintenance to the end of 2030. After that the software keeps running, but the fixes, legal changes and security patches stop arriving.
Most of what is written about this date is written by people who sell the move. This is a plainer version: what the date actually forces, and the order in which to decide.
What the date does and does not mean
It does not mean the system switches off. An ERP out of maintenance still posts invoices. What changes is risk. A tax or payroll rule changes and no update comes. A security flaw is published and no patch follows. An integration partner upgrades its side and nobody at the vendor will help with yours. Each year out of maintenance, the gap between the system and the world around it widens.
It also does not mean every business must be live on the new product by 2027. Extended maintenance exists, at a higher fee, to buy time. Buying time is a legitimate decision. Drifting into it without deciding is not.
Decision one: stay, extend or move
There are three positions, and a board should be able to say which one it has chosen.
- Move before the end of mainstream maintenance. The cleanest position, and the one with the least time left. Implementation partners are busiest in the last two years before a deadline, and rates follow.
- Take extended maintenance and move later. Costs more each year and keeps the system supported. It suits a business with a merger, a new warehouse or another large project already in the calendar.
- Leave SAP. For some mid-sized businesses the move to the new product is as large as a move to a different ERP. If so, it is fair to compare both on the same page.
The wrong position is the fourth one: no decision, and a renewal invoice that makes it by default.
Decision two: convert what exists, or start again
A move can carry the existing configuration and history across, or it can be a fresh implementation that loads only current data. The first keeps years of custom code and the habits built around it. The second is a chance to drop them, at the cost of redesigning processes people know.
The honest way to choose is to count. How many custom programs exist, and how many have run in the last year? How many reports does anyone open? How many of the interfaces still have something at the other end? A system where most of the custom work is unused is a strong case for starting again. A system where the custom work is the business is a case for converting.
Decision three: who owns the data and the testing
This is the decision most projects skip, and it is the one that moves the go-live date. The partner will configure the software. Somebody in the business has to decide which materials, customers, vendors and prices are carried across, clean them, and prove by reconciliation that what arrived matches what left. Somebody has to write test scripts from real orders and hold the gate on go-live. Who owns the data and the testing in an ERP upgrade covers both jobs.
For a supplier that trades by EDI there is a further item. Every document the old system sent to a retailer has to leave the new one in the same shape. That is a test with the trading partner, on the trading partner's calendar.
What can start now, whichever way it goes
Three pieces of work are useful under every one of the positions above, and none of them commits the business to a product.
- An inventory of what is in use. Custom programs, interfaces, reports and jobs, each marked used or unused, with an owner.
- A master data clean-up. Duplicates, inactive records, units of measure and pack sizes. Clean data shortens any migration and improves the current system on the way.
- A written list of what the system must still do on day one. Not a wish list. The transactions the business cannot trade without.
A business that has these three documents can get comparable quotes from partners. A business without them gets a discovery phase, at its own expense, that produces the same three documents.
The short version
The deadline is real, and it is a deadline for a decision more than for a go-live. Choose a position, count what is actually used, and name the people who own the data and the tests. The software choice is easier after that, and so is the conversation with whoever sells it.
Quantonic's SAP service covers support, interfaces, master data and upgrade readiness. The SAP page says what is covered and who delivers it.
Comments & Discussion
No comments yet. Be the first to share your thoughts!
Leave a Comment
Please sign in to leave a comment.